After a hurricane, an ice storm or a derecho, the county does not go looking for a tree company. It activates the contract it signed eighteen months earlier, in a quiet season, with a contractor whose prices were already on file and already written to FEMA's rules. The tree companies that work the storm are the ones on that contract or subcontracted to it. Everyone else does private driveways.
The reason is money. FEMA's Public Assistance program reimburses counties and cities for debris removal only when the contract was procured under the federal standards at 2 CFR 200 and paid on unit prices, and a county that gets it wrong pays for the storm itself. So the contracts are pre-positioned, competitively bid, priced per cubic yard, per tree, per hanger and per stump, and dominated by a small number of national debris firms who know the rules. This guide covers those rules, the real prices, what a tree company can bid directly and what it should subcontract, and how to get on the list before the season. It builds on how to get government tree care and arborist contracts.
On this page
The short version
- FEMA limits time-and-materials payment to the first 70 hours of debris work; everything after must be on unit prices by volume or weight. Cost-plus-percentage-of-cost is barred, and piggybacking another agency's contract can cost the buyer its reimbursement.
- Real 2024-25 prices: 8.62 to 8.98 dollars a cubic yard for vegetative debris on an Alabama regional award, 7.75 to 9.25 in a Georgia county after Hurricane Helene, hazardous trees 75 to 595 dollars by size, hangers 82.50 a tree, stumps 120 to 235.
- Hazardous trees, hangers and stumps are the tree company's lines. The hazard determination has to come from an ISA Certified Arborist, a TRAQ holder or a registered forester, and pruning is never eligible.
- Contracts are bid in the off-season for one-year terms with renewals and activated by declaration; the way in is the county's pre-positioned solicitation or a subcontract to the prime on the same lines.
The rules every storm contract is written to
The buyer's reimbursement depends on four federal requirements, and each one shows up as a clause in the contract.
- Competitive procurement under 2 CFR 200.317 to 200.327. Full and open competition, a cost or price analysis above the simplified acquisition threshold (250,000 dollars), and the required contract clauses (remedies over 250,000, termination over 10,000). 2 CFR 200.320 allows a noncompetitive award only when the emergency will not permit delay, which is why the contract is bid before the storm rather than after.
- Unit prices, with time and materials limited to 70 hours. FEMA's debris contracting guidance (RP9580.201) limits time-and-materials payment to the first 70 hours of actual work, the initial road-clearance push, and requires all other payment to be on unit prices by volume or weight. 2 CFR 200.318(j) allows time and materials at all only with a ceiling price and a determination that nothing else is suitable.
- No cost-plus-percentage-of-cost. 2 CFR 200.324 bars it. FEMA denied a Georgia university system's Hurricane Matthew claim because the contract was time and materials without a ceiling plus 20 percent overhead, and noted the disaster's median rate was 20.39 dollars a cubic yard against the claimed average of 49.14.
- No piggybacking. Using another agency's contract may jeopardize funding under FEMA's guidance, so each county bids its own or joins a regional joint bid written for the purpose.
FEMA's Public Assistance Program and Policy Guide, version 5 as amended in August 2025, is the current controlling document; check the current text with the buyer's emergency management office, because the guide changes between disasters.
What the contracts pay
| Line | Alabama county joint bid, Region 1 (DRC, Dec 2024 to Nov 2025) | Bulloch County, GA (Southern Disaster Recovery, Hurricane Helene, Oct 2024) |
|---|---|---|
| Vegetative debris, per cubic yard, by haul distance | 8.62 dollars under 30 miles; 8.88 for 30 to 60; 8.98 over 60 | 7.75 dollars to 15 miles; 9.25 for 15.1 to 30 |
| Construction and demolition debris | 18.86 a cubic yard or 82.50 a ton | n/a |
| Grinding / air-curtain burning, per cubic yard | 6.48 / 5.24 | n/a |
| Hazardous trees, per tree by diameter | 75 dollars at 6 to 12 inches up to 220 at 48 and over | 115 dollars at 6 to 12 inches up to 595 at 48 and over |
| Hangers, per tree (limbs 2 inches and up) | 82.50 | check the current figure with the buyer |
| Stumps, per stump | 120 at 24 to 36 inches; 190 at 36 to 48; 235 over 48 | n/a |
| Contract ceiling | Regional standby, activated by declaration | Not to exceed 3,000,000 dollars, about 250,000 cubic yards expected |
Rates move during a storm when they have to. Columbia County, Florida raised Ceres Environmental's Helene rate from 10.48 to 14.98 dollars a cubic yard for days over 4,500 yards, on a 6,000,000- to 8,000,000-dollar cleanup. Monitoring is a separate contract with its own hourly rates (Alabama Region 1: 38 dollars an hour for a field monitor, 69 for a project manager; Bulloch County: 47.58 for a monitor and 109.31 for a grant consultant), and the monitor's load tickets are what the county submits to FEMA. Hand-loaded trucks are paid at 50 percent of volume and trucks without tailgates at 85 percent, which is why the primes run certified, placarded haul units.
The first-push hourly side, before the 70 hours run out, looks like Hyde County, North Carolina's tabulation: 85 to 260 dollars an hour for a 50-foot bucket truck, 80 to 250 for a 30-ton crane, 45 to 225 for a chipper, 30 to 90 for a climber with gear, and 400 to 650 for an 850-horsepower grinder. See Unit price contract.
The tree company's lines: hazardous trees, hangers and stumps
Hauling debris by the cubic yard is a trucking business, and the national primes (DRC, Ceres, Southern Disaster Recovery, TFR and a few others) run it with subcontracted haul units. The lines that need a tree crew are the hazardous tree removals, the hangers and the stump extractions, and FEMA's Category A guidance sets the eligibility rules a tree company has to work inside:
- A hazardous tree is eligible when it is on public property or the right-of-way, the hazard was caused by the disaster, and a certified arborist, TRAQ holder or registered forester has documented the determination. Pruning, trimming and maintenance are never eligible.
- Hangers are paid per tree, not per limb; FEMA discourages per-limb pricing. The limb has to be 2 inches or more, in the right-of-way, and still hanging.
- A stump is paid per stump only if half or more of the root ball is exposed and extraction is required; otherwise it is flush-cut and paid by volume. Fill for the hole is a separate line.
The contractor's crew does the work; the monitor photographs and tickets every tree, hanger and stump with a GPS location and the arborist's determination. A tree company that already documents to that standard, and has a TRAQ holder to sign the determinations, is a subcontractor the primes want and a direct bidder a county can accept on the hazard lines. See MBE, WBE and DBE certification for government contracts.
Bidding direct versus subcontracting to the prime
Direct. Counties and regional joint bids (Alabama's county association runs one by region) solicit pre-positioned contracts on one-year terms with renewals, and many award to more than one contractor in ranked order. A tree company can bid the full schedule if it can stand up haul capacity through subcontracts, or, where the form allows partial awards, bid the hazardous tree, hanger and stump lines only. The bid needs the insurance the county sets (5,000,000-dollar umbrellas are common on storm contracts; check the current figure with the buyer), a performance bond once activated, evidence of the arborist and TRAQ credentials, a list of equipment with capacities, and references from prior declared events. Cities buy the same thing on a smaller scale as on-call emergency tree contracts: Nutley, New Jersey's required fifteen years of emergency experience and bid security of 10 percent or 20,000 dollars.
Subcontract. The primes hold contracts in dozens of counties they cannot staff at once and build subcontractor lists before the season. Registering with them, with the same credentials package, is the faster route into the first storm, at the prime's rate rather than the county's. Either way, the local advantage is real: a crew that is already in the county when the declaration comes works the first 70 hours while the prime's fleet is still on the interstate.
What the contract will require of you when it is activated
- Mobilization. A stated number of crews on site within 24 to 72 hours of the notice to proceed, with the county's emergency manager as the point of contact.
- Certified haul units. Every truck measured and placarded by the monitor before the first load; the placard sets the cubic yards paid per load.
- Documentation. Daily load tickets, hazard tree photographs and determinations, GPS locations, and crew time records for the first 70 hours. A load the monitor did not ticket does not exist.
- Debris management sites. Reduction by grinding or burning at the county's site, with environmental permits the county or prime obtains.
- Federal clauses. Equal opportunity, Davis-Bacon where it applies, the Byrd anti-lobbying certification, debarment certification and the clauses in 2 CFR 200 Appendix II. See Debarment and Emergency procurement.
Where we come in
A storm contract is bid in a quiet March for a season that may not come, on a schedule with forty lines written to a federal guide that changes between disasters. Finding the counties in your territory that are rebidding, reading the FEMA clauses in each one, and getting the credentials, equipment list and references in on time is the part that does not get done while the crews are working. We find the storm and emergency contracts you can actually win, we read every page of every one, we tell you why it fits, and we write the response, with the schedule and the federal certifications in the buyer's format. You set the prices and you sign it. Every response is built for one company and never reused. If you want to see which counties in your territory are pre-positioning this season, book a call; twenty minutes is enough to see what is open for you.
Common questions
Why does the county bid the storm contract before the storm?
Because FEMA reimburses only work procured under 2 CFR 200's competitive standards, and a noncompetitive award is allowed only when the emergency will not permit delay. A pre-positioned, competitively bid contract with unit prices is the county's insurance that the cleanup will be paid for.
Can I bill hourly on a storm contract?
Only for the first 70 hours of actual work, the initial road-clearance push, and only with a ceiling. After that FEMA requires unit prices by volume or weight, and cost-plus-percentage-of-cost is barred outright.
What does storm debris removal pay per cubic yard?
Recent awards ran 7.75 to 9.25 dollars a cubic yard for vegetative debris in Georgia after Hurricane Helene and 8.62 to 8.98 on a 2024-25 Alabama regional standby contract, with hazardous trees at 75 to 595 dollars by size and hangers at 82.50 a tree. Rates were raised mid-storm in Florida when volumes exceeded 4,500 yards a day.
Do I need TRAQ for storm work?
For the hazardous tree lines, yes in practice: FEMA's guidance requires the hazard determination to come from a certified arborist, a TRAQ holder or a registered forester, and the monitor will not ticket a tree without one.
Is it better to subcontract to a national debris prime?
For a first storm, usually. The primes build subcontractor lists before the season and pay for the hazard-tree, hanger and stump lines at their rate. Bid direct once you have a declared-event reference, the credentials and the insurance the county requires.
Sources
- FEMA, RP9580.201 Debris Removal Contracting Guidance
- 2 CFR 200.318, General procurement standards
- 2 CFR 200.320, Procurement methods
- 2 CFR 200.324, Contract cost and price
- FEMA, Public Assistance policy guidance (PAPPG v5)
- FEMA, Public Assistance debris removal guidance, Category A
- FEMA, Debris Monitoring Guide SOP (March 2021)
- FEMA appeal decision, debris removal procurement (University System of Georgia)
- Association of County Commissions of Alabama, Region 1 debris removal award, DRC (2024-25)
- Association of County Commissions of Alabama, Region 1 debris monitoring award, Thompson (2025-26)
- Statesboro Herald, Bulloch County Hurricane Helene debris removal contract (Oct 2024)
- Lake City Reporter, Columbia County storm debris contract amended (2024)
- Hyde County, NC, Emergency clearance hourly rate bid tabulation
- Township of Nutley, NJ, Emergency and Non-Emergency Tree Services bid specifications
- ISA Rocky Mountain Chapter, Tree Risk Assessment Qualification